Monthly Updates
For the month of March 2024, residents and the public can expect to see the following work being conducted on site:
- Excavation of soil and installation of structural supports to continue
For the month of February 2024, residents and the public can expect to see the following work being conducted on site:
- Excavation of soil and installation of structural supports to continue
For the month of January 2024, residents and the public can expect to see the following changes:
- Construction fencing will be installed around the development sites
- Restricted access zones (areas where pedestrians and residents cannot go) will be set up around the development sites
- Installation of lighting and security cameras around the perimeters of the construction sites
- Large equipment will be brought onto the site
- Excavation of soil and installation of structural supports to begin
- General increase in activity and an increased presence of construction workers, including staffed security booths